Skinningrove Flood Alleviation Scheme

The Environment Agency is developing a scheme to reduce the risk of flooding from Skinningrove Beck in partnership with Redcar and Cleveland Borough Council. This page has been created to work with you, keep you informed, provide updates on the proposed scheme, and offer opportunities for you to engage with us throughout the process.

Current Operations

Currently, the Environment Agency manages the manually operated flood gates and demountable parapets at Stone Row Bridge when high water levels are forecast in the beck. Deciding when to operate these defences in order to prevent flooding is difficult, as the beck can rise rapidly and sometimes with little warning. This unpredictability means the defences occasionally need to be operated at short notice and can remain closed for some time until the risk of flooding has passed. The closure of the defences is not only a challenge for us operationally but also causes disruption for residents of Zetland Row and Grove Hill who rely on the bridge for vehicle access.

Stone Row Bridge flood gates in operation

Stone Row Bridge flood gate and parapets in operation with evidence of debris build up within Skinningrove Beck

Scheme overview

Work is underway on a scheme to deliver a long term solution to this problem. The scheme involves removing Stone Row Bridge along with the flood gates and demountable parapets that form part of it. A replacement bridge will be built across the beck between New Company Row and Zetland Row next to the Riverside Building (the old village school). The deck of this new bridge will sit above the height of the flood walls which means there will be no need for flood gates at either side and ensures the residents of Zetland Row and Grove Hill will have 24/7 vehicle access to their houses, regardless of the flow in the beck.

Curious about the bridge design? Find the design in the project visualisations section

Scheme latest

The design of the scheme is now complete. The scheme was granted planning permission by Redcar and Cleveland Borough Council in February 2026 and recently received financial approval of its Full Business Case. As some residents might be aware, we began mobilising within Skinningrove on August 12th 2026 with works beginning within Magpie Wood Glampsite and around KasKane.

We have now added a Project Timeline widget to this engagement page. This will be updated weekly with an overview of what happened the week prior and what works or consultation will planned for the week ahead. All updates will be accompanied with images to keep residents fully informed as to what is happening in their village

A massive thank you to everyone who visited our community engagement event at the Skinningrove Village Hall on Thursday 4th June

All of the materials that were displayed at the event have been shared on this page. Please view Planning Documents to see construction works and traffic & pedestrian management plans, FAQs for general questions around the scheme and the vote on your favourite Bridge Railings Artwork from the options in the poll tool.

If you were unable to attend this engagement event and still have unanswered questions then feel free to get in contact via email or leave questions within our Ask a Question tool and we'll aim to get in contact ASAPPhoto taken from June 2026 community engagement event

A massive thank you to all who attended our Grove Hill Event on August 12th. Although we took a slightly different approach to this engagement event, by bringing the event to bottom end of Grove Hill allowing all residents to see our project team closer to the comfort of their homes.

We had some fantastic conversations surrounding construction, parking, noise etc and have taken on your feedback. With a target of early October for the access track through the Glampsite and changes to Grove Hill traffic routes, if you have any questions and queries then feel free to get in contact via email or leave questions within our Ask a Question tool and we'll aim to get in contact ASAP


Photo taken from August 2026 Grove Hill Event


Short video featuring some members of the project team and local residents explaining the need and benefits of the Skinningrove FAS


How do I keep updated with the scheme?

We want to keep you updated and hear your thoughts on the scheme. The best way to do this?

You should:

  • We want you to Register and Subscribe, so we can notify you of the latest news and updates on the Skinningrove FAS
  • Check the news feed for updates
  • Provide answers and feedback to any quick poll questions, forums and ideas
  • Have a look at the FAQs

We will be offering other opportunities for you to participate, such as surveys, polls or other ideas... we'll keep you posted!

Any questions? Our contact details are in the "Get in Touch!" section


Get involved now!

If you've got ideas as to how we can improve this page, use the "ideas" tool below. Or, if you have a question about the scheme, use the "ask a question" tab below.

The Environment Agency is developing a scheme to reduce the risk of flooding from Skinningrove Beck in partnership with Redcar and Cleveland Borough Council. This page has been created to work with you, keep you informed, provide updates on the proposed scheme, and offer opportunities for you to engage with us throughout the process.

Current Operations

Currently, the Environment Agency manages the manually operated flood gates and demountable parapets at Stone Row Bridge when high water levels are forecast in the beck. Deciding when to operate these defences in order to prevent flooding is difficult, as the beck can rise rapidly and sometimes with little warning. This unpredictability means the defences occasionally need to be operated at short notice and can remain closed for some time until the risk of flooding has passed. The closure of the defences is not only a challenge for us operationally but also causes disruption for residents of Zetland Row and Grove Hill who rely on the bridge for vehicle access.

Stone Row Bridge flood gates in operation

Stone Row Bridge flood gate and parapets in operation with evidence of debris build up within Skinningrove Beck

Scheme overview

Work is underway on a scheme to deliver a long term solution to this problem. The scheme involves removing Stone Row Bridge along with the flood gates and demountable parapets that form part of it. A replacement bridge will be built across the beck between New Company Row and Zetland Row next to the Riverside Building (the old village school). The deck of this new bridge will sit above the height of the flood walls which means there will be no need for flood gates at either side and ensures the residents of Zetland Row and Grove Hill will have 24/7 vehicle access to their houses, regardless of the flow in the beck.

Curious about the bridge design? Find the design in the project visualisations section

Scheme latest

The design of the scheme is now complete. The scheme was granted planning permission by Redcar and Cleveland Borough Council in February 2026 and recently received financial approval of its Full Business Case. As some residents might be aware, we began mobilising within Skinningrove on August 12th 2026 with works beginning within Magpie Wood Glampsite and around KasKane.

We have now added a Project Timeline widget to this engagement page. This will be updated weekly with an overview of what happened the week prior and what works or consultation will planned for the week ahead. All updates will be accompanied with images to keep residents fully informed as to what is happening in their village

A massive thank you to everyone who visited our community engagement event at the Skinningrove Village Hall on Thursday 4th June

All of the materials that were displayed at the event have been shared on this page. Please view Planning Documents to see construction works and traffic & pedestrian management plans, FAQs for general questions around the scheme and the vote on your favourite Bridge Railings Artwork from the options in the poll tool.

If you were unable to attend this engagement event and still have unanswered questions then feel free to get in contact via email or leave questions within our Ask a Question tool and we'll aim to get in contact ASAPPhoto taken from June 2026 community engagement event

A massive thank you to all who attended our Grove Hill Event on August 12th. Although we took a slightly different approach to this engagement event, by bringing the event to bottom end of Grove Hill allowing all residents to see our project team closer to the comfort of their homes.

We had some fantastic conversations surrounding construction, parking, noise etc and have taken on your feedback. With a target of early October for the access track through the Glampsite and changes to Grove Hill traffic routes, if you have any questions and queries then feel free to get in contact via email or leave questions within our Ask a Question tool and we'll aim to get in contact ASAP


Photo taken from August 2026 Grove Hill Event


Short video featuring some members of the project team and local residents explaining the need and benefits of the Skinningrove FAS


How do I keep updated with the scheme?

We want to keep you updated and hear your thoughts on the scheme. The best way to do this?

You should:

  • We want you to Register and Subscribe, so we can notify you of the latest news and updates on the Skinningrove FAS
  • Check the news feed for updates
  • Provide answers and feedback to any quick poll questions, forums and ideas
  • Have a look at the FAQs

We will be offering other opportunities for you to participate, such as surveys, polls or other ideas... we'll keep you posted!

Any questions? Our contact details are in the "Get in Touch!" section


Get involved now!

If you've got ideas as to how we can improve this page, use the "ideas" tool below. Or, if you have a question about the scheme, use the "ask a question" tab below.

  • Progress Update 19th & 26th October 2026

    supporting image

    Planned Works – Week Commencing 19 October

    • Completing the stone surface across the former play park area to create a safe and stable construction compound.
    • Continuing preparations to connect the new access route through the glamping site.
    • Starting installation of new site drainage infrastructure.
    • Constructing foundations for site welfare and office facilities.
    • Preparing for the next phase of works on the western side of the river.

    Planned Works – Week Commencing 26 October

    • Introducing temporary traffic lights on New Company Row to enable safe access to the construction site.
    • Beginning removal of existing hardstanding and surfaces to prepare for future flood defence works.
    • Continuing drainage and access improvement works across the site.
    • Installing temporary site facilities required to support the construction programme.
    • Progressing utility connections needed for the main construction compound.
    • Continuing preparations for upcoming bridge and flood alleviation works.

    Play Park Reinstatement

    • Following the removal of the existing play area to facilitate construction, planning is now beginning for its future reinstatement.
    • We are committed to working with local residents, families and young people to understand what they would like to see included in the replacement play area once the site compound is no longer required.
    • Further information on how the community can share ideas and feedback will be provided in future updates.

    Pre-Condition Surveys Conducted by Brown Rural

    • We are expecting to receive pre-condition survey reports for homes that had a survey conducted this year.
    • We will endeavour to provide those affected with a copy of the report in due course.

    Planned Works – Week Commencing 19 October

    • Completing the stone surface across the former play park area to create a safe and stable construction compound.
    • Continuing preparations to connect the new access route through the glamping site.
    • Starting installation of new site drainage infrastructure.
    • Constructing foundations for site welfare and office facilities.
    • Preparing for the next phase of works on the western side of the river.

    Planned Works – Week Commencing 26 October

    • Introducing temporary traffic lights on New Company Row to enable safe access to the construction site.
    • Beginning removal of existing hardstanding and surfaces to prepare for future flood defence works.
    • Continuing drainage and access improvement works across the site.
    • Installing temporary site facilities required to support the construction programme.
    • Progressing utility connections needed for the main construction compound.
    • Continuing preparations for upcoming bridge and flood alleviation works.

    Play Park Reinstatement

    • Following the removal of the existing play area to facilitate construction, planning is now beginning for its future reinstatement.
    • We are committed to working with local residents, families and young people to understand what they would like to see included in the replacement play area once the site compound is no longer required.
    • Further information on how the community can share ideas and feedback will be provided in future updates.

    Pre-Condition Surveys Conducted by Brown Rural

    • We are expecting to receive pre-condition survey reports for homes that had a survey conducted this year.
    • We will endeavour to provide those affected with a copy of the report in due course.

  • Information for Grove Hill residents

    Following feedback from residents regarding parking, BAM proposes maintaining a 3-metre clearway along Grove Hill to allow vehicles and construction traffic to pass while avoiding a full parking suspension where possible. The proposed clearway is shown in green.

    The current programme is for a full closure of the road between Grove Hill and Zetland Row from 30 November. From this date onwards vehicle access to Grove Hill will be via Magpie Wood Glamping Site. BAM will maintain pedestrian access to Zetland Row wherever practicable. Please note we are waiting for Northern Powergrid to move an electricity pole at the top end of Grove Hill in order to be able to open the temporary road through the glamping site. This is currently schedule to take place from 18 November.

    The clearway arrangement will be monitored to ensure it meets safety and access requirements. If necessary, additional measures may be introduced. However, BAM's preference is to retain parking outside properties for residents wherever possible.

    Following feedback from residents regarding parking, BAM proposes maintaining a 3-metre clearway along Grove Hill to allow vehicles and construction traffic to pass while avoiding a full parking suspension where possible. The proposed clearway is shown in green.

    The current programme is for a full closure of the road between Grove Hill and Zetland Row from 30 November. From this date onwards vehicle access to Grove Hill will be via Magpie Wood Glamping Site. BAM will maintain pedestrian access to Zetland Row wherever practicable. Please note we are waiting for Northern Powergrid to move an electricity pole at the top end of Grove Hill in order to be able to open the temporary road through the glamping site. This is currently schedule to take place from 18 November.

    The clearway arrangement will be monitored to ensure it meets safety and access requirements. If necessary, additional measures may be introduced. However, BAM's preference is to retain parking outside properties for residents wherever possible.

  • Progress Update 12 October 2026

    Progress last week (week commencing 5 October)

    • The site compound on the playing field continues to be established. More than 1,200 tonnes of stone have been delivered and placed to create a robust working platform for construction vehicles, plant and materials.
    • Removal of the play area surfacing and perimeter fencing has continued to make way for the site compound.
    • Construction of the new access track through the glamping site towards the Grove Hill tie-in point is ongoing, including vegetation clearance, earthworks and formation of the route.
    • Preparatory works on the existing glamping site access track have been completed, including planing of the existing surface and tie-in areas ahead of resurfacing.
    • Security hoarding around the site compound is progressing well and is now approximately 60% complete, helping to ensure the safety of both the public and site operatives.

    Planned Works this week (week commencing 12 October)

    • Installation of a new tarmac surface to the access track through the glamping site in preparation for use by Grove Hill residents.
    • Continued removal of remaining play area equipment, surfacing and associated infrastructure.
    • Completion of stone placement, grading and compaction across the site compound to provide the final working surface.
    • Completion of the compound security measures, including installation of remaining hoarding sections and access gates.
    • Ongoing preparation works for the connection between the glamping site access route and Grove Hill, including final groundworks and formation works.

    We would like to thank local residents, visitors and businesses for their continued patience while these essential works are undertaken. Every effort is being made to minimise disruption while safely progressing the project.


    Progress last week (week commencing 5 October)

    • The site compound on the playing field continues to be established. More than 1,200 tonnes of stone have been delivered and placed to create a robust working platform for construction vehicles, plant and materials.
    • Removal of the play area surfacing and perimeter fencing has continued to make way for the site compound.
    • Construction of the new access track through the glamping site towards the Grove Hill tie-in point is ongoing, including vegetation clearance, earthworks and formation of the route.
    • Preparatory works on the existing glamping site access track have been completed, including planing of the existing surface and tie-in areas ahead of resurfacing.
    • Security hoarding around the site compound is progressing well and is now approximately 60% complete, helping to ensure the safety of both the public and site operatives.

    Planned Works this week (week commencing 12 October)

    • Installation of a new tarmac surface to the access track through the glamping site in preparation for use by Grove Hill residents.
    • Continued removal of remaining play area equipment, surfacing and associated infrastructure.
    • Completion of stone placement, grading and compaction across the site compound to provide the final working surface.
    • Completion of the compound security measures, including installation of remaining hoarding sections and access gates.
    • Ongoing preparation works for the connection between the glamping site access route and Grove Hill, including final groundworks and formation works.

    We would like to thank local residents, visitors and businesses for their continued patience while these essential works are undertaken. Every effort is being made to minimise disruption while safely progressing the project.


  • CLOSURE: Skinningrove Play Park

    As of Thursday 10th September, the play park and playing field off Mill Lane will be closed for the duration of the ongoing Flood Alleviation Scheme. As previously stated, this will be the location of BAM's compound and will be operational with construction vehicles, staff and other works.

    We understand that there is some disappointment that the current play park will be removed and the playing field will be out of use, but in the coming weeks and months we will be engaging with residents as to what YOU would like to see put back as we are work to

    As of Thursday 10th September, the play park and playing field off Mill Lane will be closed for the duration of the ongoing Flood Alleviation Scheme. As previously stated, this will be the location of BAM's compound and will be operational with construction vehicles, staff and other works.

    We understand that there is some disappointment that the current play park will be removed and the playing field will be out of use, but in the coming weeks and months we will be engaging with residents as to what YOU would like to see put back as we are work to replace and upgrade the existing equipment.

    Look out for updates on play park consultations here, on the EHQ page or via Facebook groups.

    If you have any questions, feel free to contact us via email: SkinningroveFAS@environment-agency.gov.uk

  • Upcoming Works: Northern Power Grid

    Impact on some residents likely

    Northern Power Grid (NPG) and contractors, Freedom, will be present within the village starting Thursday 20th August until Friday 28th August. During this period NPG and/or contractors Freedom, will undertake multiple activities in and around the playing field

    Thursday 20th August

    NPG staff will begin installation of new steel pole, works include excavating a pole hole, installing the pole and letting the concrete infill set around the pole. This area will be cordoned off as the works are ongoing and the concrete sets

    Monday 24th August

    NPG contractors Freedom to begin the excavation from the

    Impact on some residents likely

    Northern Power Grid (NPG) and contractors, Freedom, will be present within the village starting Thursday 20th August until Friday 28th August. During this period NPG and/or contractors Freedom, will undertake multiple activities in and around the playing field

    Thursday 20th August

    NPG staff will begin installation of new steel pole, works include excavating a pole hole, installing the pole and letting the concrete infill set around the pole. This area will be cordoned off as the works are ongoing and the concrete sets

    Monday 24th August

    NPG contractors Freedom to begin the excavation from the newly installed Steel pole across the playing field and up to the pole at the side of Mill Lane. This is scheduled for 3 days including the installation of the new Low Voltage cable. This should have no impact on traffic

    Friday 28th August

    There is set to be a Localised Power Outage as the works include the dropping of the existing overhead wires across the field area and connection/energise the new Low Voltage cable. These works are scheduled for most of this day with the Power Outage affecting some, but not all residents from 09:00 – 14:00.

    We apologise for any inconvenience caused due to the works, any updates will be posted here.

    If you have any questions, feel free to contact us via email: SkinningroveFAS@environment-agency.gov.uk

    If you would like to more information on NPG's planned power cuts, to understand what they will be doing and why, please visit www.northernpowergird.com/planned-power-cuts.


  • Upcoming works: Ground Investigation Survey

    Ground Investigation works are set to begin Monday 24th August, lasting approximately 10-13 days.

    The location of these works will start from in Magpie Wood Glampsite before moving towards the lower end of the playing field and KasKane area. There should be little to no impact on traffic during this time.

    Any question feel free to email: SkinningroveFAS@environment-agency.gov.uk

    Ground Investigation works are set to begin Monday 24th August, lasting approximately 10-13 days.

    The location of these works will start from in Magpie Wood Glampsite before moving towards the lower end of the playing field and KasKane area. There should be little to no impact on traffic during this time.

    Any question feel free to email: SkinningroveFAS@environment-agency.gov.uk

  • Upcoming works: Garage Demolition

    From Tuesday 11th August, demolition of 3 garages between Zetland Row and Grove Hill will begin.

    This work should only affect the immediate footpath nearest the bottom-most garage. BAM will be onsite to oversee this with some areas (pathways) out of use until the works are complete. The steps that come down adjacent to the top garage will be out of use during this time so please find a suitable alternative route. The road between Grove Hill and Zetland Row should see little impact so traffic impact will be kept to a minimum.

    An excavator and van will park within

    From Tuesday 11th August, demolition of 3 garages between Zetland Row and Grove Hill will begin.

    This work should only affect the immediate footpath nearest the bottom-most garage. BAM will be onsite to oversee this with some areas (pathways) out of use until the works are complete. The steps that come down adjacent to the top garage will be out of use during this time so please find a suitable alternative route. The road between Grove Hill and Zetland Row should see little impact so traffic impact will be kept to a minimum.

    An excavator and van will park within the site fencing, and possibly impact the nearest lane during loading but residents will be kept informed.

    Any questions feel free to contact our email: SkinningroveFAS@environment-agency.gov.uk

  • Grove Hill In-person Event: Wednesday 12th August

    As a follow-up to the community engagement event held at the Village Hall in June, we would like to invite residents to attend our information drop-in event regarding the Skinningrove Flood Alleviation Scheme.

    We have carefully considered the comments and questions raised and would like to provide Grove Hill residents with a further opportunity to learn more about the scheme, discuss the proposed works in greater detail, and receive additional feedback to help to shape our approach moving forward.

    Event Details:
    📍 Location: North end of Grove Hill - We will be set up with a stand under a gazebo

    As a follow-up to the community engagement event held at the Village Hall in June, we would like to invite residents to attend our information drop-in event regarding the Skinningrove Flood Alleviation Scheme.

    We have carefully considered the comments and questions raised and would like to provide Grove Hill residents with a further opportunity to learn more about the scheme, discuss the proposed works in greater detail, and receive additional feedback to help to shape our approach moving forward.

    Event Details:
    📍 Location: North end of Grove Hill - We will be set up with a stand under a gazebo
    📅 Date: Wednesday 12th August 2026
    ⏰ Time: 4:00pm to 6:30pm

    Residents are welcome to attend at any time during the drop-in period.

    This session is intended to build upon the discussions held at our previous engagement, and as well as allow residents who did not attend, an opportunity to speak directly with the project team.

    If you are unable to attend but would like further information, please continue to follow project updates through the Skinningrove Flood Alleviation Scheme EHQ page or contact us via email: SkinningroveFAS@environment-agency.gov.uk

  • Upcoming Works: Deflection testing

    Upcoming works for the Skinningrove FAS on Tuesday 4th August at Painted bridge with deflection testing works from approx. 9:30am - 3pm.

    There will be a traffic impacts in this area, creating a single file traffic, as temporary traffic lights will be deployed in the morning before the works begin. The Deepdale Cove Holiday Park entrance will remain open during these works.

    If works overrun, the deflection testing may continue through to Wednesday 5th August

    Any questions about these surveys, feel free to contact our email: SkinningroveFAS@environment-agency.gov.uk(External link)

    Upcoming works for the Skinningrove FAS on Tuesday 4th August at Painted bridge with deflection testing works from approx. 9:30am - 3pm.

    There will be a traffic impacts in this area, creating a single file traffic, as temporary traffic lights will be deployed in the morning before the works begin. The Deepdale Cove Holiday Park entrance will remain open during these works.

    If works overrun, the deflection testing may continue through to Wednesday 5th August

    Any questions about these surveys, feel free to contact our email: SkinningroveFAS@environment-agency.gov.uk(External link)

  • Upcoming Works: Pre-condition surveys

    On Thursday 2nd July and Friday 3rd July, you might see the following work being undertaken around the village:

    - Pre-condition survey works

    These surveys should not interrupt traffic routes or cause any issues for residents.

    Any questions about these surveys, feel free to contact our email: SkinningroveFAS@environment-agency.gov.uk

    On Thursday 2nd July and Friday 3rd July, you might see the following work being undertaken around the village:

    - Pre-condition survey works

    These surveys should not interrupt traffic routes or cause any issues for residents.

    Any questions about these surveys, feel free to contact our email: SkinningroveFAS@environment-agency.gov.uk