Skinningrove Flood Alleviation Scheme
The Environment Agency is developing a scheme to reduce the risk of flooding from Skinningrove Beck in partnership with Redcar and Cleveland Borough Council. This page has been created to work with you, keep you informed, provide updates on the proposed scheme, and offer opportunities for you to engage with us throughout the process.
Current Operations
Currently, the Environment Agency manages the manually operated flood gates and demountable parapets at Stone Row Bridge when high water levels are forecast in the beck. Deciding when to operate these defences in order to prevent flooding is difficult, as the beck can rise rapidly and sometimes with little warning. This unpredictability means the defences occasionally need to be operated at short notice and can remain closed for some time until the risk of flooding has passed. The closure of the defences is not only a challenge for us operationally but also causes disruption for residents of Zetland Row and Grove Hill who rely on the bridge for vehicle access.
Stone Row Bridge flood gates in operation
Stone Row Bridge flood gate and parapets in operation with evidence of debris build up within Skinningrove Beck
Scheme overview
Work is underway on a scheme to deliver a long term solution to this problem. The scheme involves removing Stone Row Bridge along with the flood gates and demountable parapets that form part of it. A replacement bridge will be built across the beck between New Company Row and Zetland Row next to the Riverside Building (the old village school). The deck of this new bridge will sit above the height of the flood walls which means there will be no need for flood gates at either side and ensures the residents of Zetland Row and Grove Hill will have 24/7 vehicle access to their houses, regardless of the flow in the beck.
Curious about the bridge design? Find the design in the project visualisations section
Scheme latest
The design of the scheme is now complete. The scheme was granted planning permission by Redcar and Cleveland Borough Council in February 2026 and recently received financial approval of its Full Business Case. As some residents might be aware, we began mobilising within Skinningrove on August 12th 2026 with works beginning within Magpie Wood Glampsite and around KasKane.
We have now added a Project Timeline widget to this engagement page. This will be updated weekly with an overview of what happened the week prior and what works or consultation will planned for the week ahead. All updates will be accompanied with images to keep residents fully informed as to what is happening in their village
A massive thank you to everyone who visited our community engagement event at the Skinningrove Village Hall on Thursday 4th June
All of the materials that were displayed at the event have been shared on this page. Please view Planning Documents to see construction works and traffic & pedestrian management plans, FAQs for general questions around the scheme and the vote on your favourite Bridge Railings Artwork from the options in the poll tool.
If you were unable to attend this engagement event and still have unanswered questions then feel free to get in contact via email or leave questions within our Ask a Question tool and we'll aim to get in contact ASAPPhoto taken from June 2026 community engagement event
A massive thank you to all who attended our Grove Hill Event on August 12th. Although we took a slightly different approach to this engagement event, by bringing the event to bottom end of Grove Hill allowing all residents to see our project team closer to the comfort of their homes.
We had some fantastic conversations surrounding construction, parking, noise etc and have taken on your feedback. With a target of early October for the access track through the Glampsite and changes to Grove Hill traffic routes, if you have any questions and queries then feel free to get in contact via email or leave questions within our Ask a Question tool and we'll aim to get in contact ASAP
Photo taken from August 2026 Grove Hill Event Short video featuring some members of the project team and local residents explaining the need and benefits of the Skinningrove FAS
How do I keep updated with the scheme?
We want to keep you updated and hear your thoughts on the scheme. The best way to do this?
You should:
- We want you to Register and Subscribe, so we can notify you of the latest news and updates on the Skinningrove FAS
- Check the news feed for updates
- Provide answers and feedback to any quick poll questions, forums and ideas
- Have a look at the FAQs
We will be offering other opportunities for you to participate, such as surveys, polls or other ideas... we'll keep you posted!
Any questions? Our contact details are in the "Get in Touch!" section
Get involved now!
If you've got ideas as to how we can improve this page, use the "ideas" tool below. Or, if you have a question about the scheme, use the "ask a question" tab below.
The Environment Agency is developing a scheme to reduce the risk of flooding from Skinningrove Beck in partnership with Redcar and Cleveland Borough Council. This page has been created to work with you, keep you informed, provide updates on the proposed scheme, and offer opportunities for you to engage with us throughout the process.
Current Operations
Currently, the Environment Agency manages the manually operated flood gates and demountable parapets at Stone Row Bridge when high water levels are forecast in the beck. Deciding when to operate these defences in order to prevent flooding is difficult, as the beck can rise rapidly and sometimes with little warning. This unpredictability means the defences occasionally need to be operated at short notice and can remain closed for some time until the risk of flooding has passed. The closure of the defences is not only a challenge for us operationally but also causes disruption for residents of Zetland Row and Grove Hill who rely on the bridge for vehicle access.
Stone Row Bridge flood gates in operation
Stone Row Bridge flood gate and parapets in operation with evidence of debris build up within Skinningrove Beck
Scheme overview
Work is underway on a scheme to deliver a long term solution to this problem. The scheme involves removing Stone Row Bridge along with the flood gates and demountable parapets that form part of it. A replacement bridge will be built across the beck between New Company Row and Zetland Row next to the Riverside Building (the old village school). The deck of this new bridge will sit above the height of the flood walls which means there will be no need for flood gates at either side and ensures the residents of Zetland Row and Grove Hill will have 24/7 vehicle access to their houses, regardless of the flow in the beck.
Curious about the bridge design? Find the design in the project visualisations section
Scheme latest
The design of the scheme is now complete. The scheme was granted planning permission by Redcar and Cleveland Borough Council in February 2026 and recently received financial approval of its Full Business Case. As some residents might be aware, we began mobilising within Skinningrove on August 12th 2026 with works beginning within Magpie Wood Glampsite and around KasKane.
We have now added a Project Timeline widget to this engagement page. This will be updated weekly with an overview of what happened the week prior and what works or consultation will planned for the week ahead. All updates will be accompanied with images to keep residents fully informed as to what is happening in their village
A massive thank you to everyone who visited our community engagement event at the Skinningrove Village Hall on Thursday 4th June
All of the materials that were displayed at the event have been shared on this page. Please view Planning Documents to see construction works and traffic & pedestrian management plans, FAQs for general questions around the scheme and the vote on your favourite Bridge Railings Artwork from the options in the poll tool.
If you were unable to attend this engagement event and still have unanswered questions then feel free to get in contact via email or leave questions within our Ask a Question tool and we'll aim to get in contact ASAPPhoto taken from June 2026 community engagement event
A massive thank you to all who attended our Grove Hill Event on August 12th. Although we took a slightly different approach to this engagement event, by bringing the event to bottom end of Grove Hill allowing all residents to see our project team closer to the comfort of their homes.
We had some fantastic conversations surrounding construction, parking, noise etc and have taken on your feedback. With a target of early October for the access track through the Glampsite and changes to Grove Hill traffic routes, if you have any questions and queries then feel free to get in contact via email or leave questions within our Ask a Question tool and we'll aim to get in contact ASAP
Photo taken from August 2026 Grove Hill Event Short video featuring some members of the project team and local residents explaining the need and benefits of the Skinningrove FAS
How do I keep updated with the scheme?
We want to keep you updated and hear your thoughts on the scheme. The best way to do this?
You should:
- We want you to Register and Subscribe, so we can notify you of the latest news and updates on the Skinningrove FAS
- Check the news feed for updates
- Provide answers and feedback to any quick poll questions, forums and ideas
- Have a look at the FAQs
We will be offering other opportunities for you to participate, such as surveys, polls or other ideas... we'll keep you posted!
Any questions? Our contact details are in the "Get in Touch!" section
Get involved now!
If you've got ideas as to how we can improve this page, use the "ideas" tool below. Or, if you have a question about the scheme, use the "ask a question" tab below.
-
Riverside Building Car Park 13 November 2026
A visit to site today provided a good opportunity to see first-hand the progress being made in the car park of the Riverside Building.
Teams have been busy this week carrying out preparatory works ready for piling to commence on 25 November for the new bridge abutment. With this key milestone approaching, it's positive to see the site taking shape and preparations progressing well.
Hope everyone has a good weekend.
Chris

A visit to site today provided a good opportunity to see first-hand the progress being made in the car park of the Riverside Building.
Teams have been busy this week carrying out preparatory works ready for piling to commence on 25 November for the new bridge abutment. With this key milestone approaching, it's positive to see the site taking shape and preparations progressing well.
Hope everyone has a good weekend.
Chris

-
Weekly Update 9 November 2026
Last week, we completed the removal of boundary fencing, brickwork and sections of tarmac within the Riverside Building car park. These works have helped prepare the area for the next phase of construction activities.
We also completed site clearance works on the eastern side of the beck where the former garages were demolished. This area is now ready for Northern Powergrid to begin its planned utility diversion works from 16 November.
On Friday 6 November, we hand-delivered letters to residents of Grove Hill providing an update on the planned opening of the temporary access road through the glamping site. Subject to the completion of ongoing utility diversion works, we currently expect the road to become operational from Monday 30 November 2026. We are currently awaiting Northern Powergrid's relocation of the existing electricity pole at the tie-in point before the final connection can be completed. These works are currently scheduled to take place on Wednesday 18 November, after which construction of the tie-in can commence. We handed out car permits which residents are asked to display on their dashboard when driving through the glamping site.
Preparation of the Riverside Building car park for piling
Entrance to site compound opposite KasKane
Preparation of the site of the former garages ready for Northern PowergridLooking Ahead to This Week
Our planned activities for this week include:
• Temporary closure of the footpath between Zetland Row and the pedestrian bridge to allow construction activities to be carried out safely.
• Commencing construction of the piling mat within the Riverside Building car park. A piling mat is a specially constructed working platform that provides a stable foundation for heavy construction plant and machinery.
As always, we will continue to monitor and minimise disruption wherever possible and would like to thank the local community for its continued patience and support while these works progress.
Last week, we completed the removal of boundary fencing, brickwork and sections of tarmac within the Riverside Building car park. These works have helped prepare the area for the next phase of construction activities.
We also completed site clearance works on the eastern side of the beck where the former garages were demolished. This area is now ready for Northern Powergrid to begin its planned utility diversion works from 16 November.
On Friday 6 November, we hand-delivered letters to residents of Grove Hill providing an update on the planned opening of the temporary access road through the glamping site. Subject to the completion of ongoing utility diversion works, we currently expect the road to become operational from Monday 30 November 2026. We are currently awaiting Northern Powergrid's relocation of the existing electricity pole at the tie-in point before the final connection can be completed. These works are currently scheduled to take place on Wednesday 18 November, after which construction of the tie-in can commence. We handed out car permits which residents are asked to display on their dashboard when driving through the glamping site.
Preparation of the Riverside Building car park for piling
Entrance to site compound opposite KasKane
Preparation of the site of the former garages ready for Northern PowergridLooking Ahead to This Week
Our planned activities for this week include:
• Temporary closure of the footpath between Zetland Row and the pedestrian bridge to allow construction activities to be carried out safely.
• Commencing construction of the piling mat within the Riverside Building car park. A piling mat is a specially constructed working platform that provides a stable foundation for heavy construction plant and machinery.
As always, we will continue to monitor and minimise disruption wherever possible and would like to thank the local community for its continued patience and support while these works progress.
-
Weekly Update Friday 30 October 2026
This week, we have installed the site cabins within the construction compound. These facilities will provide office space, welfare facilities, a kitchen, and toilets for the site team as work progresses.
In the short term, the cabins will be powered by a temporary generator while we await a permanent mains electricity connection from Northern Powergrid.
You may also have noticed that we have started removing sections of boundary fencing and brickwork within the Riverside Building car park. Temporary traffic lights have also been installed on New Company Row to support these activities and ensure works can be carried out safely.


Looking Ahead to Next Week
Our planned activities for next week include:
• Removal of boundary fencing and walls at the tie-in point between Grove Hill and the adjacent glamping site, where the temporary access route will be established.
• Clearance of tree stumps and vegetation within the Riverside Building car park to prepare the area for upcoming construction activities.
• Construction of a piling mat within the Riverside Building car park will commence. A piling mat is a specially constructed working platform that provides a stable foundation for piling rigs and other heavy construction equipment to operate safely across the site.
As always, we will continue to monitor and minimise disruption wherever possible and thank the community for its continued patience and support while these works are undertaken.
This week, we have installed the site cabins within the construction compound. These facilities will provide office space, welfare facilities, a kitchen, and toilets for the site team as work progresses.
In the short term, the cabins will be powered by a temporary generator while we await a permanent mains electricity connection from Northern Powergrid.
You may also have noticed that we have started removing sections of boundary fencing and brickwork within the Riverside Building car park. Temporary traffic lights have also been installed on New Company Row to support these activities and ensure works can be carried out safely.


Looking Ahead to Next Week
Our planned activities for next week include:
• Removal of boundary fencing and walls at the tie-in point between Grove Hill and the adjacent glamping site, where the temporary access route will be established.
• Clearance of tree stumps and vegetation within the Riverside Building car park to prepare the area for upcoming construction activities.
• Construction of a piling mat within the Riverside Building car park will commence. A piling mat is a specially constructed working platform that provides a stable foundation for piling rigs and other heavy construction equipment to operate safely across the site.
As always, we will continue to monitor and minimise disruption wherever possible and thank the community for its continued patience and support while these works are undertaken.
-
Progress Update 19th & 26th October 2026
Planned Works – Week Commencing 19 October
- Completing the stone surface across the former play park area to create a safe and stable construction compound.
- Continuing preparations to connect the new access route through the glamping site.
- Starting installation of new site drainage infrastructure.
- Constructing foundations for site welfare and office facilities.
- Preparing for the next phase of works on the western side of the river.
Planned Works – Week Commencing 26 October
- Introducing temporary traffic lights on New Company Row to enable safe access to the construction site.
- Beginning removal of existing hardstanding and surfaces to prepare for future flood defence works.
- Continuing drainage and access improvement works across the site.
- Installing temporary site facilities required to support the construction programme.
- Progressing utility connections needed for the main construction compound.
- Continuing preparations for upcoming bridge and flood alleviation works.
Play Park Reinstatement
- Following the removal of the existing play area to facilitate construction, planning is now beginning for its future reinstatement.
- We are committed to working with local residents, families and young people to understand what they would like to see included in the replacement play area once the site compound is no longer required.
- Further information on how the community can share ideas and feedback will be provided in future updates.
Pre-Condition Surveys Conducted by Brown Rural
- We are expecting to receive pre-condition survey reports for homes that had a survey conducted this year.
- We will endeavour to provide those affected with a copy of the report in due course.
Planned Works – Week Commencing 19 October
- Completing the stone surface across the former play park area to create a safe and stable construction compound.
- Continuing preparations to connect the new access route through the glamping site.
- Starting installation of new site drainage infrastructure.
- Constructing foundations for site welfare and office facilities.
- Preparing for the next phase of works on the western side of the river.
Planned Works – Week Commencing 26 October
- Introducing temporary traffic lights on New Company Row to enable safe access to the construction site.
- Beginning removal of existing hardstanding and surfaces to prepare for future flood defence works.
- Continuing drainage and access improvement works across the site.
- Installing temporary site facilities required to support the construction programme.
- Progressing utility connections needed for the main construction compound.
- Continuing preparations for upcoming bridge and flood alleviation works.
Play Park Reinstatement
- Following the removal of the existing play area to facilitate construction, planning is now beginning for its future reinstatement.
- We are committed to working with local residents, families and young people to understand what they would like to see included in the replacement play area once the site compound is no longer required.
- Further information on how the community can share ideas and feedback will be provided in future updates.
Pre-Condition Surveys Conducted by Brown Rural
- We are expecting to receive pre-condition survey reports for homes that had a survey conducted this year.
- We will endeavour to provide those affected with a copy of the report in due course.
-
Information for Grove Hill residents
Following feedback from residents regarding parking, BAM proposes maintaining a 3-metre clearway along Grove Hill to allow vehicles and construction traffic to pass while avoiding a full parking suspension where possible. The proposed clearway is shown in green.
The current programme is for a full closure of the road between Grove Hill and Zetland Row from 30 November. From this date onwards vehicle access to Grove Hill will be via Magpie Wood Glamping Site. BAM will maintain pedestrian access to Zetland Row wherever practicable. Please note we are waiting for Northern Powergrid to move an electricity pole at the top end of Grove Hill in order to be able to open the temporary road through the glamping site. This is currently schedule to take place from 18 November.
The clearway arrangement will be monitored to ensure it meets safety and access requirements. If necessary, additional measures may be introduced. However, BAM's preference is to retain parking outside properties for residents wherever possible.
Following feedback from residents regarding parking, BAM proposes maintaining a 3-metre clearway along Grove Hill to allow vehicles and construction traffic to pass while avoiding a full parking suspension where possible. The proposed clearway is shown in green.
The current programme is for a full closure of the road between Grove Hill and Zetland Row from 30 November. From this date onwards vehicle access to Grove Hill will be via Magpie Wood Glamping Site. BAM will maintain pedestrian access to Zetland Row wherever practicable. Please note we are waiting for Northern Powergrid to move an electricity pole at the top end of Grove Hill in order to be able to open the temporary road through the glamping site. This is currently schedule to take place from 18 November.
The clearway arrangement will be monitored to ensure it meets safety and access requirements. If necessary, additional measures may be introduced. However, BAM's preference is to retain parking outside properties for residents wherever possible.
-
Progress Update 12 October 2026
Progress last week (week commencing 5 October)
- The site compound on the playing field continues to be established. More than 1,200 tonnes of stone have been delivered and placed to create a robust working platform for construction vehicles, plant and materials.
- Removal of the play area surfacing and perimeter fencing has continued to make way for the site compound.
- Construction of the new access track through the glamping site towards the Grove Hill tie-in point is ongoing, including vegetation clearance, earthworks and formation of the route.
- Preparatory works on the existing glamping site access track have been completed, including planing of the existing surface and tie-in areas ahead of resurfacing.
- Security hoarding around the site compound is progressing well and is now approximately 60% complete, helping to ensure the safety of both the public and site operatives.
Planned Works this week (week commencing 12 October)
- Installation of a new tarmac surface to the access track through the glamping site in preparation for use by Grove Hill residents.
- Continued removal of remaining play area equipment, surfacing and associated infrastructure.
- Completion of stone placement, grading and compaction across the site compound to provide the final working surface.
- Completion of the compound security measures, including installation of remaining hoarding sections and access gates.
- Ongoing preparation works for the connection between the glamping site access route and Grove Hill, including final groundworks and formation works.
We would like to thank local residents, visitors and businesses for their continued patience while these essential works are undertaken. Every effort is being made to minimise disruption while safely progressing the project.


Progress last week (week commencing 5 October)
- The site compound on the playing field continues to be established. More than 1,200 tonnes of stone have been delivered and placed to create a robust working platform for construction vehicles, plant and materials.
- Removal of the play area surfacing and perimeter fencing has continued to make way for the site compound.
- Construction of the new access track through the glamping site towards the Grove Hill tie-in point is ongoing, including vegetation clearance, earthworks and formation of the route.
- Preparatory works on the existing glamping site access track have been completed, including planing of the existing surface and tie-in areas ahead of resurfacing.
- Security hoarding around the site compound is progressing well and is now approximately 60% complete, helping to ensure the safety of both the public and site operatives.
Planned Works this week (week commencing 12 October)
- Installation of a new tarmac surface to the access track through the glamping site in preparation for use by Grove Hill residents.
- Continued removal of remaining play area equipment, surfacing and associated infrastructure.
- Completion of stone placement, grading and compaction across the site compound to provide the final working surface.
- Completion of the compound security measures, including installation of remaining hoarding sections and access gates.
- Ongoing preparation works for the connection between the glamping site access route and Grove Hill, including final groundworks and formation works.
We would like to thank local residents, visitors and businesses for their continued patience while these essential works are undertaken. Every effort is being made to minimise disruption while safely progressing the project.


-
CLOSURE: Skinningrove Play Park
As of Thursday 10th September, the play park and playing field off Mill Lane will be closed for the duration of the ongoing Flood Alleviation Scheme. As previously stated, this will be the location of BAM's compound and will be operational with construction vehicles, staff and other works.
We understand that there is some disappointment that the current play park will be removed and the playing field will be out of use, but in the coming weeks and months we will be engaging with residents as to what YOU would like to see put back as we are work toContinue reading
As of Thursday 10th September, the play park and playing field off Mill Lane will be closed for the duration of the ongoing Flood Alleviation Scheme. As previously stated, this will be the location of BAM's compound and will be operational with construction vehicles, staff and other works.
We understand that there is some disappointment that the current play park will be removed and the playing field will be out of use, but in the coming weeks and months we will be engaging with residents as to what YOU would like to see put back as we are work to replace and upgrade the existing equipment.
Look out for updates on play park consultations here, on the EHQ page or via Facebook groups.
If you have any questions, feel free to contact us via email: SkinningroveFAS@environment-agency.gov.uk
-
Upcoming Works: Northern Power Grid
Impact on some residents likely
Northern Power Grid (NPG) and contractors, Freedom, will be present within the village starting Thursday 20th August until Friday 28th August. During this period NPG and/or contractors Freedom, will undertake multiple activities in and around the playing field
Thursday 20th August
NPG staff will begin installation of new steel pole, works include excavating a pole hole, installing the pole and letting the concrete infill set around the pole. This area will be cordoned off as the works are ongoing and the concrete sets
Monday 24th August
NPG contractors Freedom to begin the excavation from theContinue reading
Impact on some residents likely
Northern Power Grid (NPG) and contractors, Freedom, will be present within the village starting Thursday 20th August until Friday 28th August. During this period NPG and/or contractors Freedom, will undertake multiple activities in and around the playing field
Thursday 20th August
NPG staff will begin installation of new steel pole, works include excavating a pole hole, installing the pole and letting the concrete infill set around the pole. This area will be cordoned off as the works are ongoing and the concrete sets
Monday 24th August
NPG contractors Freedom to begin the excavation from the newly installed Steel pole across the playing field and up to the pole at the side of Mill Lane. This is scheduled for 3 days including the installation of the new Low Voltage cable. This should have no impact on traffic
Friday 28th August
There is set to be a Localised Power Outage as the works include the dropping of the existing overhead wires across the field area and connection/energise the new Low Voltage cable. These works are scheduled for most of this day with the Power Outage affecting some, but not all residents from 09:00 – 14:00.
We apologise for any inconvenience caused due to the works, any updates will be posted here.
If you have any questions, feel free to contact us via email: SkinningroveFAS@environment-agency.gov.uk
If you would like to more information on NPG's planned power cuts, to understand what they will be doing and why, please visit www.northernpowergird.com/planned-power-cuts.
-
Upcoming works: Ground Investigation Survey
Ground Investigation works are set to begin Monday 24th August, lasting approximately 10-13 days.
The location of these works will start from in Magpie Wood Glampsite before moving towards the lower end of the playing field and KasKane area. There should be little to no impact on traffic during this time.
Any question feel free to email: SkinningroveFAS@environment-agency.gov.uk
Ground Investigation works are set to begin Monday 24th August, lasting approximately 10-13 days.
The location of these works will start from in Magpie Wood Glampsite before moving towards the lower end of the playing field and KasKane area. There should be little to no impact on traffic during this time.
Any question feel free to email: SkinningroveFAS@environment-agency.gov.uk
-
Upcoming works: Garage Demolition
From Tuesday 11th August, demolition of 3 garages between Zetland Row and Grove Hill will begin.
This work should only affect the immediate footpath nearest the bottom-most garage. BAM will be onsite to oversee this with some areas (pathways) out of use until the works are complete. The steps that come down adjacent to the top garage will be out of use during this time so please find a suitable alternative route. The road between Grove Hill and Zetland Row should see little impact so traffic impact will be kept to a minimum.
An excavator and van will park withinContinue reading
From Tuesday 11th August, demolition of 3 garages between Zetland Row and Grove Hill will begin.
This work should only affect the immediate footpath nearest the bottom-most garage. BAM will be onsite to oversee this with some areas (pathways) out of use until the works are complete. The steps that come down adjacent to the top garage will be out of use during this time so please find a suitable alternative route. The road between Grove Hill and Zetland Row should see little impact so traffic impact will be kept to a minimum.
An excavator and van will park within the site fencing, and possibly impact the nearest lane during loading but residents will be kept informed.
Any questions feel free to contact our email: SkinningroveFAS@environment-agency.gov.uk
-
Please get in touch with the team with any queries or comments on the scheme
Environment Agency
-
Project Updates - w/c 7th September
Skinningrove Flood Alleviation Scheme has finished this stageWhat happened last week:
- Prestart walkover undertaken with BAM, EA, Jacobs, WSP and the Council.
- Excavation of trial holes in and around Magpie Wood Glampsite and KasKane Cafe
What's happening this week:
- Completion of boreholes and demobilisation from site
- BAM to set up fencing surrounding playground and Deepdale bridge
- Topsoil strip within the Deepdale bridge area
Trial holes near KasKane CafeIf you have any questions, feel free to contact us via email: SkinningroveFAS@environment-agency.gov.uk
-
Project Update - w/c 14th September
Skinningrove Flood Alleviation Scheme has finished this stageWhat happened last week:
- Dunelm completed ground investigation works in and around Magpie Wood Glamping Site and KasKane Cafe. These works were undertaken to establish the depth and condition of underground mine workings.

- BAM started setting up their site compound. Fencing has now been installed around the field and play park.

What's happening this week:
- BAM will start constructing the haul road across Deepdale Bridge and through Magpie Wood Glamping Site.
If you have any questions, feel free to contact us via email: SkinningroveFAS@environment-agency.gov.uk
- Dunelm completed ground investigation works in and around Magpie Wood Glamping Site and KasKane Cafe. These works were undertaken to establish the depth and condition of underground mine workings.
-
Project Updates - w/c 21st September
Skinningrove Flood Alleviation Scheme has finished this stageWhat happened last week:
- Geogrid & Stone delivery for Deepdale works
- Commencement of topsoil strip in site compound
- Plate load testing for Haul Road and Cabin Foundations
- Installation of stone to entranceway of Deepdale
- Continuation of GPR survey to Riverside Carpark, Zetland Row and compound area.
What's happening this week:
- Continuation of topsoil strip within park area.
- Complete stone placement and compaction across the haul road and Deepdale bridge
- Begin to remove playpark surfacing & equipment
Deepdale topsoil stripping leading into site compound
-
Project Update - w/c 21 September
Skinningrove Flood Alleviation Scheme is currently at this stageWhat happened last week:
- BAM continued to establish their site compound at the park including the stripping of top soil and installation of a stone surface across Deepdale Bridge to permit deliveries of materials.
What's happening this week:
Continue top soil strip within park area.
Complete stone placement and compaction across the haul road and Deepdale bridge
Begin to remove playpark surfacing and equipment.
- What will the scheme involve?
- Why is the scheme needed?
- When will construction be starting and how long will the work take?
- How much will the scheme cost and is this best use of public funding?
- Where will the new bridge be constructed?
- Why can’t you just replace the existing bridge?
- Wouldn’t working upstream to slow the flow naturally be a more cost-effective and sustainable way to reduce flood risk in the village?
- Why are you not providing a footbridge to Stone Row?
- What are the benefits of the scheme?
- Why can’t you just automate the flood gates?
- Is all the disruption worth it in the long run?
- How will communication be managed – will there be regular updates?
- Will there be opportunities to provide feedback during construction?
- Are you just walking away from Skinningrove, post scheme?
- Will there be work at weekends or bank holidays?
- Which roads will construction traffic use during the scheme?
- How will I access Zetland Row and Grove Hill during construction?
- Will the road through the glamping site be gritted in winter?
- I live on Grove Hill. Where will I leave my car during periods of restricted parking?
- How much notice will we get on the parking restrictions?
- How often will parking be restricted?
- Can I still get deliveries, tradespeople, etc. during parking restrictions?
- I have a disability and require my car to be close to my property; how will this impact me?
- Will there be a constant stream of lorries and other construction vehicles driving past my house every day?
- What right do you have to tell me I can't park outside my house?
- Car parking is already at a premium in the village what are your plans to ensure all resident have adequate parking for their vehicles at or within easy access to their properties post-construction, especially those in Zetland Row and Grove Hill?
-
04 June 2026
Do you play Minecraft? Do you have an interest in this Flood Alleviation Scheme and our role in climate change, the environment, and reducing the impacts of flooding?
You need to download our RiverCraft World Mod!
This allows you to explore and understand the key areas of the Environment Agency’s work through three games themed around flood mitigation, climate change, and the local environment.
LINK: RiverCraft | Minecraft Education
Curious on how it works? Watch the video walkthrough on YouTube: RiverCraft Guide - YouTube
*Minecraft PC and Download required*





