Progress Update 19th & 26th October 2026

Planned Works – Week Commencing 19 October

  • Completing the stone surface across the former play park area to create a safe and stable construction compound.
  • Continuing preparations to connect the new access route through the glamping site.
  • Starting installation of new site drainage infrastructure.
  • Constructing foundations for site welfare and office facilities.
  • Preparing for the next phase of works on the western side of the river.

Planned Works – Week Commencing 26 October

  • Introducing temporary traffic lights on New Company Row to enable safe access to the construction site.
  • Beginning removal of existing hardstanding and surfaces to prepare for future flood defence works.
  • Continuing drainage and access improvement works across the site.
  • Installing temporary site facilities required to support the construction programme.
  • Progressing utility connections needed for the main construction compound.
  • Continuing preparations for upcoming bridge and flood alleviation works.

Play Park Reinstatement

  • Following the removal of the existing play area to facilitate construction, planning is now beginning for its future reinstatement.
  • We are committed to working with local residents, families and young people to understand what they would like to see included in the replacement play area once the site compound is no longer required.
  • Further information on how the community can share ideas and feedback will be provided in future updates.

Pre-Condition Surveys Conducted by Brown Rural

  • We are expecting to receive pre-condition survey reports for homes that had a survey conducted this year.
  • We will endeavour to provide those affected with a copy of the report in due course.