• Beckingham Marshes - background investigations towards developing a business case continue

    Progress on this project has been impacted by ongoing recovery works. However, we continue to develop investigations and development of a business case which is aimed at repairing a dewatering structure that is coming to the end of its life and compliance with the reservoir act. Investigation works and analysis are ongoing and supporting the funding allocation by outlining costs for the SSBC. The project team have secured moderation funding to support the project up to SSBC submission, further moderation funding is pending approval for next year and beyond.

  • Barton to New Holland Tidal Flood Alleviation Scheme - exploring funding opportunities and planning ahead

    Click here to find out more about the Barton Scheme

    The Outline Business Case (OBC) was submitted by late May. However, there is still a substantial funding gap based on current estimates. The project team have a plan to reduce costs whilst trying to explore additional funding opportunities. Support from North Lincolnshire Council has been obtained through their Strategic Water Management Board.

    Following OBC approval the project team will be focussed on detailed design, consents and approvals. They will also continue with necessary ecology surveys and second phase of ground investigation. Construction is now expected over a number of years. However, embankment repairs at Barrow Haven may be able to be undertaken beforehand, after necessary investigations and surveys over the next year.

    The project’s Resilience Advisory Group continue to be informed of progress, and further guidance will be sought from the Steering Group regarding the quantified funding gap. North Lincolnshire Council have been approached to make a funding contribution to aid this situation.

  • Birthday Buoy! Celebrating one year of the Spurn wave buoy deployment

    June 2025 marks the first anniversary of the wave buoy deployed 3km southeast of Spurn Point, as part of the Humber Strategic Monitoring Programme.
    The buoy fills a crucial gap in the North Sea’s monitoring network, positioned between the Hornsea buoy to the north and the Chapel Point buoy to the south. We’ve worked closely with the National Network of Regional Coastal Monitoring Programmes and their contractors, as well as the National Oceanography Centre, and the Humber Harbour Authority, ABP, to develop and deliver this project.

    Over the past year, the buoy has been hard at work, collecting vital data on:

    🌊 Wave height, length and direction
    🌡️ Sea surface temperature

    This data helps us identify short-term variations in the sea state, and longer-term trends in the wave climate at the mouth of the estuary, providing insights we can integrate into technical assessments and monitoring.

    Importantly, this data will help us better understand the critical role played by Spurn Point – the iconic sand and shingle spit that stretches south from the Holderness coast into the Humber – in shielding the estuary from the full brunt of North Sea waves.

    🔗 Want to dive deeper? Check out the links below to find out more about the monitoring programme, Spurn Point, and how the landscape has changed over time.


    Images courtesy of Fugro 2024
  • Stallingborough Phase 3 Sea Defence Improvements - revetment works near completion

    The 3rd year of construction activities commenced early in March, with consent from Natural England. The four small rock amour in-fill areas are due to be installed later this summer. This will complete the defence revetment works.

    The access track to the outfall of New Cut Drain has been completed, and the design to cross over the Anglian Water main sewers has been approved. The installation is expected to be completed by the Autumn. At Oldfleet Drain the design of the overflow has been developed collaboratively with key stakeholders and the construction of the access track to the outfall is underway. The MMO have given the required consents for the desilting work to start using a dredging barge.

    New Cut Drain Outfall access track


    The funding contribution from National Highways has been received and this should enable additional resilience works to the outfalls to be undertaken within the project. The project will be able to ensure no net loss to biodiversity through the planting of an enhanced seed mix along some of the landward berm. The project team also continue to explore the possibility of further environmental enhancement of the adjacent saltmarsh.

  • Strategy Update - Understanding Risk around the Humber

    The Humber 2100+ project team have now completed the technical work for Step 1 (Understand Risk) of the project and presented the full set of outputs to partners. The 'Understand Risk' step is about building a solid foundation of evidence to create an accurate picture of future tidal flood risk around the Humber – essentially ensuring a common understanding of the challenge we face.

    The outputs were presented for partner 'endorsement' via a summary report and a detailed evidence pack in January. 9 of the 11 local authority partners in the project, and the Environment Agency, have now formally endorsed the outputs, (including the picture of risk, the methodology and data behind them). We are confident that formal endorsement from the remaining partners will follow very shortly. This is a key milestone for the project as these outputs will form the basis for understanding strategic flood risk across the Humber going forwards. They will inform Step 2 of the project, as well as shaping our ongoing investment on the ground. Having positive endorsement from all partners means that we will be able to work together on an adaptive approach to managing tidal risk across the interconnected estuary system.

    Work is now underway to begin Step 2, with a number of key areas of work progressing. These include a governance review; consideration of the evidence required to ‘agree approaches’ for managing tidal flood risk; and reflections on the lessons learned from Step 1. The partnership is also working on ways to present the Step 1 outputs to the wider public.




  • Outstrays to Skeffling Managed Realignment (OtSMRS) - Pumping station and breach works resume

    OtSMRS continues to attract visitors. Over the winter, there were many different varieties of birds, a diverse range of other species and visitors particularly have enjoyed the new bridleway and bird hides. Work paused during the winter to protect the over-wintering birds, but the site team have begun to remobilise enabling work to resume.

    In early January, a small material slip occurred resulting in some emergency work to improve and minimise the likelihood of it reoccurring. Around the same time, the Skeffling pumping station compound was flooded due to a power cut to the existing pumping station. However, there was no significant damage.


    Further erosion of the breach occurred over the winter months. However, the breach still requires further expansion to better accommodate the flow of water out from the site. The MMO (Marine Management Organisation) licence has been approved and the HRA (Habitats Regulations Appraisal) has been updated to reflect this work. The works are due to be carried out in late spring/early summer when the site is likely to be drier and will better support plant movement.

    The Skeffling pumping station works have resumed and should be complete by the winter. Work on Winestead pumping station (a separate Environment Agency project, being delivered under this contract with consultants for efficiency) will begin in earnest this year.

    Click here to find out more about the Outstrays to Skeffling Managed Realignment site

  • Middle Humber - Capital Maintenance Programme (MH-CaMP) - progress on work packages


    The project team have produced an overarching ‘Mega’ business case which was approved in July 24. The various workshops held previously have informed this work to identify key stakeholders, risks and opportunities (including environmental) to support proposed future work.

    The proposal for the Middle Humber programme will start with an initial ‘bundle’ of three work packages, located on the left-bank of the Dutch River upstream of Goole and either side of the River Ouse at Reedness and Yokefleet. Currently the project team are finalising elements to be able to progress the first bundle of work. One of the key projects within this programme is large scale maintenance works to the existing defences on the north bank of the Dutch River. This has been allocated £2 million Grant in Aid (GiA) funding for 25/26, with an additional contribution from the Goole Town Deal. This will significantly reduce flood risk to around 500 homes and over 300 non-residential properties. The work will be completed by March 2027.


  • Beckingham Marshes - meeting the reservoir compliance rules

    Work to determine the best means of repairing the sluice gate at Beckingham Marshes is continuing. The project will continue to progress measures to implement remedial works to uphold the standards of the Reservoir Act 1075.

    A single stage business case is being developed which is aimed at reviewing, repairing, or potentially replacing a dewatering structure that is coming to the end of its life. investigation works and analysis are ongoing and supporting the funding allocation by outlining costs.

  • Barton to New Holland Tidal Flood Alleviation Scheme - responding to funding challenges

    The project team worked hard to develop the project appraisal and completed the Outline Business Case in January. This business case is being revised based on new information and construction is now likely to begin in 2027. However, the economic business case for the project is likely to remain very robust as it reduces flood risk to around 1300 properties.

    Both the project Steering Group and Resilience Advisory Group are being kept informed and North Lincolnshire Council will be approached for a contribution towards developing the Full Business Case. The project team continues to explore options to reduce costs.


  • Stallingborough Phase 3 Sea Defence Improvements - 3rd stage of construction activities to commence

    Over the winter months, works were paused to protect the nearby sensitive habitats within the estuary. The project team have continued to work with the consultants and the contractors to refine and coordinate all the activities involved in increasing resilience to the river outfalls. This has included further modelling to determine the best arrangement for Oldfleet Drain overflow system, and other required water control structures. The Marine Licence to desilt the foreshore has been granted by the Marine Management Organisation (MMO).

    Much work has also been undertaken to determine the best way to access New Cut Drain outfall, given the additional challenges of contaminated ground and the major sewers crossing the existing access point. Now that the necessary agreements, consents and planning elements are in place, work is being carried out via a staged approach to construct the access and enable inspections to take place before refurbishment begins later this year.

    Minor rock armour enhancements have been completed in four locations along the revetment and environmental enhancement opportunities continue to be explored.


    New Cut Drain outfall (left) and EA's Rosper Road Land, near Port of Immingham (right)