We use cookies to ensure our site functions properly and to store limited information about your usage. You may give or withdraw consent at any time. To find out more, read our privacy policy and cookie policy.
Manage Cookies
A cookie is information stored on your computer by a website you visit. Cookies often store your settings for a website, such as your preferred language or location. This allows the site to present you with information customized to fit your needs. As per the GDPR law, companies need to get your explicit approval to collect your data. Some of these cookies are ‘strictly necessary’ to provide the basic functions of the website and can not be turned off, while others if present, have the option of being turned off. Learn more about our Privacy and Cookie policies. These can be managed also from our cookie policy page.
Strictly necessary cookies(always on):
Necessary for enabling core functionality. The website cannot function properly without these cookies. This cannot be turned off. e.g. Sign in, Language
Analytics cookies:
Analytical cookies help us to analyse user behaviour, mainly to see if the users are able to find and act on things that they are looking for. They allow us to recognise and count the number of visitors and to see how visitors move around our website when they are using it. Tools used: Google Analytics
We're in the midst of constructing a £30 million Flood Storage Reservoir (FSR) to protect 191 properties and businesses from repeatedly devastating flood in the village of Lowdham in Nottinghamshire. The reservoir will protect the community from a 1 in 100 year flood event (1% Annual Exceedance Probability).
Here at the Environment Agency, we are engaging with those affected by the flooding and with the wider community to provide a timeline of the project and other useful resources. Register and subscribe to receive notifications when we share updates.
Please see our Partners and Contacts widget for further information on local action, surface water, planning and more. Click 'more' under contacts to see the full list.
Join Ben, a member of our project team, as he gives a virtual tour of the site (December 2024).
See the latest drone footage of the site taken in March. Courtesy of Nottinghamshire County Council.
We're in the midst of constructing a £30 million Flood Storage Reservoir (FSR) to protect 191 properties and businesses from repeatedly devastating flood in the village of Lowdham in Nottinghamshire. The reservoir will protect the community from a 1 in 100 year flood event (1% Annual Exceedance Probability).
Here at the Environment Agency, we are engaging with those affected by the flooding and with the wider community to provide a timeline of the project and other useful resources. Register and subscribe to receive notifications when we share updates.
Please see our Partners and Contacts widget for further information on local action, surface water, planning and more. Click 'more' under contacts to see the full list.
Join Ben, a member of our project team, as he gives a virtual tour of the site (December 2024).
See the latest drone footage of the site taken in March. Courtesy of Nottinghamshire County Council.
Lowdham Cocker Beck Flood Storage Reservoir has finished this stage
10/23 - Construction began with the ground-breaking event.
2 - Flow Control Structure Built
Lowdham Cocker Beck Flood Storage Reservoir has finished this stage
12/2024 - The Cocker Beck was diverted from it's original channel to our new temporary channel. The Flow Control Structure (FCS) was completed - this structure will mostly be covered underneath the embankment but is the critical infrastructure which will reduce the flow of the beck down to the village below.
3 - Fill the Existing beck
Lowdham Cocker Beck Flood Storage Reservoir is currently at this stage
04/2025 - 06/2025 - We need to fill in where the Cocker Beck used to flow to ensure that the new flow comes through the storage reservoir.
4 - Cut off Slurry Wall
this is an upcoming stage for Lowdham Cocker Beck Flood Storage Reservoir
07/2025 - 12/2025 - Once the reservoir fills with water, our Reservoir Construction Engineer needs to ensure water is prevented from flowing underneath the embankment as it may cause instability. To counter this, we construct what's called a cut off slurry wall. This is where we excavate a trench whilst back-filling with a bentonite clay mix, a material that is impermeable for water to flow through.
5 - North Embankment Works
this is an upcoming stage for Lowdham Cocker Beck Flood Storage Reservoir
10/2025 - 06/2025 - We'll now be at the stage to begin erecting the embankments of the reservoir! Much of the material used will come from the site itself.
6 - South Embankment Works
this is an upcoming stage for Lowdham Cocker Beck Flood Storage Reservoir
04/2026 - 08/2026 - We'll now do the same for the South Embankment.
7 - Basin Earthworks
this is an upcoming stage for Lowdham Cocker Beck Flood Storage Reservoir
10/2026 - 12/2026 - The basin of the reservoir will act as a wonderful wetland with excellent biodiversity value.
8 - Access Track
this is an upcoming stage for Lowdham Cocker Beck Flood Storage Reservoir
10/2026 - 03/2027 - The reservoir will require regular maintenance by our Asset Performance Team and therefore we will build an access track for our vehicles to get on to and around the site.
9 - Project Completion
this is an upcoming stage for Lowdham Cocker Beck Flood Storage Reservoir
04/2027 - 06/2027 - Once the grass has grown on the sides of the embankment, it will be fully stable and ready for the orifice plate to be installed on the Flow Control Structure. The orifice plate is what restricts the flow down to the village. Once the orifice plate is fitted, the storage area will be fully functioning and operational!
Note that there is often little work in the schedule in winter times (Nov - Mar). This is because the site is often too wet in winter to be able to undertake earthworks. However, if we're able to work during the winter time, we will. This may bring the completion date forward if weather is favourable.