Lowdham Cocker Beck Flood Storage Reservoir


We're in the midst of constructing a £30 million Flood Storage Reservoir (FSR) to protect 191 properties and businesses from repeatedly devastating flood in the village of Lowdham in Nottinghamshire. The reservoir will protect the community from a 1 in 100 year flood event (1% Annual Exceedance Probability).

Here at the Environment Agency, we are engaging with those affected by the flooding and with the wider community to provide a timeline of the project and other useful resources. Register and subscribe to receive notifications when we share updates.

Please see our Partners and Contacts widget for further information on local action, surface water, planning and more. Click 'more' under contacts to see the full list.




See the latest tour of the site - June 2026



See a previous tour of the construction site - September 2025




Please see a previous tour of the construction site - June 2025




Please see the update from Ben on the Lambley Road drainage works - May 2025


191 Properties better protected once the scheme is constructed. £49 million in whole life benefits afforded by the scheme. 1% AEP (Annual Exceedance probability) is the standard of protection the scheme will provide. 100,000 metres cubed of storage capacity once the reservoir is complete. Over 800m in length of embankments to be constructed using site-won material. 0 tonnes of earth to be removed from the site.


Drone Footage of the site earthworks and the Lambley Lane drainage works - June 2024. Courtesy of Nottinghamshire County Council.


See drone footage of the site taken - March 2025. Courtesy of Nottinghamshire County Council.







There are three levels of flood warnings you can sign up for. Flood alert: Flooding is possible, be prepared. Low-lying land and roads may be affected. Flood warning: Flood is expected, take action. Property flooding is likely. Severe flood warning: danger to life, prepare to evacuate. Follow the instructions of emergency services.

QR code to sign up for flood alerts and warnings.





We're in the midst of constructing a £30 million Flood Storage Reservoir (FSR) to protect 191 properties and businesses from repeatedly devastating flood in the village of Lowdham in Nottinghamshire. The reservoir will protect the community from a 1 in 100 year flood event (1% Annual Exceedance Probability).

Here at the Environment Agency, we are engaging with those affected by the flooding and with the wider community to provide a timeline of the project and other useful resources. Register and subscribe to receive notifications when we share updates.

Please see our Partners and Contacts widget for further information on local action, surface water, planning and more. Click 'more' under contacts to see the full list.




See the latest tour of the site - June 2026



See a previous tour of the construction site - September 2025




Please see a previous tour of the construction site - June 2025




Please see the update from Ben on the Lambley Road drainage works - May 2025


191 Properties better protected once the scheme is constructed. £49 million in whole life benefits afforded by the scheme. 1% AEP (Annual Exceedance probability) is the standard of protection the scheme will provide. 100,000 metres cubed of storage capacity once the reservoir is complete. Over 800m in length of embankments to be constructed using site-won material. 0 tonnes of earth to be removed from the site.


Drone Footage of the site earthworks and the Lambley Lane drainage works - June 2024. Courtesy of Nottinghamshire County Council.


See drone footage of the site taken - March 2025. Courtesy of Nottinghamshire County Council.







There are three levels of flood warnings you can sign up for. Flood alert: Flooding is possible, be prepared. Low-lying land and roads may be affected. Flood warning: Flood is expected, take action. Property flooding is likely. Severe flood warning: danger to life, prepare to evacuate. Follow the instructions of emergency services.

QR code to sign up for flood alerts and warnings.




Page last updated: 19 Oct 2026, 08:09 AM