Progress on site set up 2 April 2026
Site set up is progressing as planned. The base layer of aggregate over the saturated ground to enable heavy vehicle access is now complete and track matting is being laid. This will ensure lorries taking waste away can easily access and leave the site, even if we get further rain.
|
|
|
The aggregate is now all laid. It is raised higher than the surrounding saturated ground. |
Laying track matting over the aggregate so that heavy vehicles can manoeuvre on site |
![]() Site welfare cabins have been delivered and installed
|
A sign at the entrance to the site has been erected.
|
![]() Thermal probes before installation
|
![]() |
We regularly carry out below surface temperature monitoring of the waste. We have installed thermal probes for monitoring temperatures in the waste piles. We do this to reduce the risk and impacts of a fire to the local community, road network and infrastructure. | |


