Spring tides and upcoming works - 30 January

Ahead of spring tides next week: the weather currently looks favourable, with wave heights under 1.5m (although this may change).
Tide times aren’t ideal, so we’ll be starting work early on Monday and Tuesday (05:00). We apologise for any disruption – we’re still repairing the damage from early January, and these tides allow us to work on the lower beach and maintain the crest to continue protecting your homes.

Upcoming works:
• Beach material import: From 14/15 March for 3 weeks (weather dependent).
• Bypass operation: Planned for week commencing 23 February, moving shingle from Langney Point to Martello 64 (subject to material availability).
We thank you for your patience and for the warmth you’ve been showing the team. It’s really appreciated