The Outstrays - October 2026 Update

The works to The Outstrays are now substantially complete, and the works at the new Skeffling pumping station are complete. The old pumping station has been successfully demolished, and the contractor will be handing over this element of the work this Autumn. The larger Winestead pumping station is due to be completed in Summer 2027, with the demolition of the Outstrays pumping station to follow this.