The Outstrays - November 2026 Update


What a year it has been! With dry weather providing excellent working conditions, we have made the most of every opportunity. The new Skeffling pumping station is now complete, and substantial progress has been made at Winestead helping to keep the programme on track and delivering long-term benefits for the local community and wildlife.


Update on Skeffling and Winestead Pumping Stations

Skeffling Pumping Station

The new Skeffling pumping station will be formally handed over to the Environment Agency by the end of the year. This is slightly later than planned to allow time for some of the minor improvements to be made to the station's telemetry system.

The old Skeffling pumping station was demolished in September, with final site works due to be completed this autumn. The remaining works relate to planting a mix of native hedgerows and deciduous trees, including maple, cherry and oak. Deer-proof fencing will be erected to protect the new planting whilst it becomes established.

Three views of the Skeffling Pumping Station demolition, with an excavator removing concrete and exposed reinforced structures.Figure 1: Demolition of the existing Skeffling Pumping StationThe transformation of the former construction compound off Long Lane is complete. The new public car park is now open with space for 20 vehicles, improving access to The Outsrays and the surrounding area. This will make it easier for visitors to enjoy the site.Two additional interpretation panels will be erected, one in the new car park and the other on the embankment close to the old Skeffling pumping station. These boards will provide information about the site and a map to help visitors explore the area.


Winestead Pumping Station

Work on Winestead pumping station is progressing well and is currently forecast to be completed in spring 2027.

Much has been achieved in 2026 including the installation of the large screw pumps, excavation of the inlet and outlet channel and installation of the gantry and control systems.

Pump delivery and installation at Winestead Pumping Station, showing a pump transported by lorry and lifted into position by cranes.Figure 2: Pumps being delivered to site; pumps being installed at Winestead Pumping Station (pictures left to right)


Winestead Pumping Station under construction, showing the new pumping structures beside the watercourse.Figure 3: A picture showing current progress with the construction of the Winestead pumping Station


As we move into 2027, we will finish off installation of the remaining mechanical and electrical equipment and complete testing and commissioning required to bring the station into operation.

Once the pumping station is fully operational, we will build the new length of flood embankment across Winestead Drain to connect the Sunk Island embankment with the new embankment around The Outstrays. Demolition of the existing Outstrays pumping station will follow, with all works expected to be finished by the end of the next year.

To help protect local birdlife during upcoming construction and future demolition works, we will be installing a small amount of temporary bird netting at the Outstrays pumping station. The netting will be limited to specific parts of the existing structure where birds could otherwise establish nests. Preventing nesting before works begin reduces the risk of birds being disturbed and helps us complete the work outside of the more sensitive periods for the Humber's internationally important bird populations.


Fishing platforms

It's great to see the newly installed fishing platforms on Winestead Drain being well-used and enjoyed. We were delighted to receive this feedback:

"Called in yesterday to take a look. What I saw was one of the best sights I have had in 27 years of working in Fisheries! Thank you to you, your colleagues, and the contractors for doing such an excellent job! All the anglers we have encountered or heard from say that they are the best fishing platforms they have seen in the 40 to 60 years they have been fishing."


New wooden fishing platforms installed along the bank of Winestead DrainFigure 4: New fishing platforms on Winestead Drain


New fishing platform with steps and a wooden handrail providing acess down the bankFigure 5: Steps installed on new fishing platforms on Winestead Drain


If you're visiting the fishing platforms, please can we ask you to use the designated parking areas. Thank you for your help.



Access on the Outstrays: Paths and Bridleways

Some temporary access restrictions remain in place while construction continues, to ensure visitor safety. Please follow on-site signage and use the designated routes.

a) From the Eastern (Skeffling) end of the scheme

In the last newsletter we mentioned our intention to remove the existing diversion onto Long Lane and open the bridleway along the embankment, once work on the new Skeffling pumping station was completed. Whilst the pumping station works are now complete, currently the gate across the embankment top is still in place and walkers are directed to continue to follow the diversion.

This delay to opening the bridleway is to allow time for us to finalise a design that will meet required bridleway access standards, whilst limiting vehicle access on top of the embankment. Once reopened, this route will not be suitable for all visitors. Wheelchair users and other disabled visitors should follow the route to the bridleway from the new Skeffling car park.

b) From the Western (Outstrays) End

The temporary diversion of the King Charles III England Coast Path (ECP) remains in place while work continues on the new Winestead Pumping Station. Following agreement with ERYC, the diversion will continue until spring 2027, when the Winestead Pumping Station is expected to be complete and the new permanent route can be opened.

If you are planning a walk in the area, you can check the latest route for this section of the coast path at the ECP interactive webssite; King Charles III England Coast Path - North East Map and Information - National Trails. Simply click on the map for the trail running from the Humber Bridge to Easington and enlarge the section from Sunk Island to Skeffling to see the route.

The track to the existing Outstrays pumping station is now closed to the public. This is due to the excavation of the inlet and outlet channels to connect the new pumping station to Winestead Drain, which permanently cuts across this path. Access to this area will be reinstated once the existing pumping station is demolished in autumn 2027.

Please follow all on-site instructions and do not climb over gates and fences where signs indicate that there is no public access. These restrictions are to ensure the safety of the public.


Connecting bridleways

The new bridleway through Haverfield, connecting two existing ‘dead-end’ bridleways at each end of the site, one off Sheep Trod Lane and the other from Mulberry Lane, is expected to be completed and operational by the end of 2026. In November vegetation clearance will be undertaken, followed by the installation of the horse gate and fencing. The land along the route of the bridleway will be dedicated by the EA to ERYC, with the council then taking on its future maintenance. The layout of the horse gate and how it is operated can be seen below.


Horse and rider using a wooden horse gate to access a field.Figure 6: A photo of a horse gate being used


Managing and monitoring The Outstrays

As we develop proposals for the long-term management of the Outstrays, we will continue to manage and monitor the site, supporting public access while building our understanding of how its habitats are developing. JBA Bentley’s ecology team will continue this monitoring work throughout 2027.

It is really encouraging to have seen eels utilising the specially installed eel pass at Skeflling pumping station.


Elvers using the eel pass, with an arrow indicating their location in the shallow water.Figure 7: Elvers using the eel pass


This initial monitoring is focused on establishing a clear picture of how the site is developing following the breach. This includes tracking changes in habitats and vegetation, recording how plant communities are establishing, and observing how wildlife uses the site. We are also monitoring physical conditions such as water levels, which play a key role in shaping these new environments.

This data will help us build a picture of how the site is evolving and provide a baseline against which future changes can be measured. Over time, this will allow us to assess how well the site is functioning as a whole and whether it is meeting its environmental objectives.

Over winter, we’ll also be replacing some trees that have struggled to establish following the hot, dry summer, helping the planting develop as intended.


CIEEM award

The Outstrays project was recently shortlisted for the Chartered Institute of Ecology and Environmental Management (CIEEM) award for the ‘Best Practice Large-Scale Design for Mitigation, Compensation and Enhancement’ category where the project received the accolade of Highly Commended.


Six representatives of The Outstrays project team standing together, with two people holding framed ‘Highly Commended’ award certificates.Figure 8: Representatives of The Outstrays projecct team holding the 'Highly Commended' award




Contact Us

Environment Agency

For enquiries, please email: Welwick.Skeffling@environment-agency.gov.uk or phone our National Customer Contact Centre on 03708 506506 and ask for Anthony Kidd, Project Manager.

JBA Bentley

For enquiries about the work on site, contact Paul Craig, the site manager on 07837 454048.