Middle Humber - October 2026 Update

Work on Package 5 (Saltmarshe to Yokefleet) continues to be prioritised, due to this being the package with the highest strategic priority. This package is currently going through scoping and contractual sign-off with delivery partners (Arup and BAM) for work required to deliver the Outline Business Case (OBC).

Due to the pressing nature of the foreshore condition on sections of the Dutch River (right bank), the ‘Bank slips’ Package 1 has successfully gained additional funding and is also now progressing through scoping and contractual sign-off with delivery partners (Arup and BAM) for work required to deliver the OBC.

Categories: Middle Humber
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>