We were aware of cracking that had developed in the flood embankments along Barrow Haven during the recent prolonged dry weather and have taken action to address the issue. Our Field Team spent four days carrying out repairs by filling the cracks and, on this occasion, trialled a new method to improve the effectiveness of the work. We are hopeful that this approach will provide an effective solution while assessments continue to explore options for managing flood risk along Barrow Haven. Potential measures could be incorporated into a future adaptation phase, should additional funding become available.