April 2026 - Brownshill Staunch Sluice
Works Update
Funding has been secured and contractors appointed to carry out improvement works at Brownshill Staunch Sluice during 2025–27. These works are due to be completed by March 2027.
We have now completed the surveys needed to plan the works and the replacement sluice gates are being prepared and painted for installation.
Programme
- Phase One (March to May 2026): Preparation work, including final gate inspections and preparations, design checks, surveys, and testing of equipment.
- Phase Two (May to March 2026-2027): Main works, replace the existing sluice gates, ropes, and associated equipment, followed by final testing.
What this means for you
- The public footpath over the sluice will need to be temporarily diverted during construction for safety.
- The lock will remain open, but there may be short interruptions while works are carried out.
- Advance notice of any restrictions will be shared.
These improvements will help ensure the sluice continues to operate safely and reliably. Thank you for your patience while the works take place.