January 2029

Victoria Road Flood Alleviation Scheme

Planned: Investigations are underway to identify potential options for flood alleviation schemes within the Victoria Road area.

January 2029

Ruislip Gardens Flood Alleviation Scheme

Planned: Investigations are underway to identify potential options for flood alleviation schemes for the Ruislip Gardens estate.

March 2028

Cannon Brook Flood Alleviation Scheme

Planned: Hillingdon Council are currently developing a design for a flood alleviation scheme to protect Wallington Close properties from flooding from Cannon Brook.


March 2028

Joel Street Ditch Flood Resilience Scheme

Planned: Hillingdon Council are currently exploring funding options to deliver a flood resilience scheme within the Joel Street Ditch catchment.

April 2027

Bessingby Park Phase 2

Planned: Hillingdon Council are exploring the creation of additional attenuation basins further north in the park to reduce the risk of surface water flooding to Whitby Road properties.

March 2027

Spider Park Daylighting Project

Planned: Hillingdon Council plan on daylighting and re-naturalising of an existing Thames Water surface water sewer that currently runs through Bridgewater Road Fields (known as Spider Park). This will slow the flow of water entering the Yeading Brook, reducing the risk of flooding to residential properties downstream.

November 2026

Optimising Gully Cleansing Regime

Planned: Hillingdon Council is undertaking a risk- and evidence-based review of the gully network to define risk profiles and prioritise maintenance in higher risk areas.

October 2026

Pinn Meadows Natural Flood Management (NFM) Project

Planned: The scheme will involve the meandering of Elma's Ditch, the extension of an existing pond, and the reinstatement of an existing flood defence bund. These works will provide over 500m³ of temporary flood storage, reducing the risk of flooding to surrounding residential properties.

September 2026

Park Wood Natural Flood Management (NFM) Project

Completed: The scheme will involve the installation of NFM measures, including leaky dams and ponds, to attenuate surface water flowing towards Broadwood Avenue properties. The project will also improve access within the woods by redirecting floodwaters away from the footpaths.

Woodland area with standing water and a small leaky dam structure.

September 2026

Bessingby Park Drainage Improvement Works

Completed: The scheme will involve deepening and widening the existing attenuation basins and using the excavated material to increase the height of the bund along the southern park boundary in order to reduce the risk of future surface water flooding to Whitby Road properties.

Attenuation basin within Bessingby Park, designed to temporarily store surface water during heavy rainfall. The scheme will increase storage capacity and improve flood protection for nearby properties.


February 2026

Bourne Primary School Drainage Clearance Works

Completed: Hillingdon Council arranged for the school's drainage network to be cleared to help ensure it operates effectively.

December 2025

Cherry Close Drainage Clearance Works

Completed: Thames Water completed a full survey and clearance of the surface water drainage network.

December 2025

Ruislip Gardens Drainage Improvement Works

Completed: Hillingdon Council installed additional gullies to capture more runoff, while Thames Water undertook a full survey and clearance of the surface water drainage network.

Photograph of a brick drainage culvert surrounded by muddy soil and dense green vegetation. The culvert features a small arched opening.

September 2025

Beech Avenue Highway Reprofiling Works

Completed: Hillingdon Council completed reprofiling works to reduce the risk of surface water flooding to residential properties from the highway.

June 2025

Ruislip Gardens Flood Action Group Formed

Completed: Hillingdon Council helped form a resident-led Flood Action Group at Ruislip Gardens estate to increase community flood resilience and awareness of flood risk.

April 2025

Whitby Road Flood Action Group Formed

Completed: Hillingdon Council helped form a resident-led Flood Action Group at Whitby Road to increase community flood resilience and awareness of flood risk.